Our engineer, Mr Mbogo, sends the following progress report. We are getting there! 
Exterior Walls- Painting 99% Complete
Courtyard (Gathering Space) 95% complete
Podium – 95% Complete
Compound – 60% Complete
Matron Rooms- 100% Complete
In addition: Perimeter Wall -100% Complete - Septic Tank/Water Treatment Plant- 100% complete - Rehabilitation of 1st Floor Sanitation- 100% Complete - 2nd Floor Sanitation- 100% Complete